• 全部
主办单位:煤炭科学研究总院有限公司、中国煤炭学会学术期刊工作委员会
截水帷幕在露天煤矿截渗减排中的应用
  • Title

    Application of water cutoff curtain in the seepage cutoff and drainage reduction of open-pit coal mine

  • 作者

    张雁黄选明彭巍朱明诚曹海东刘玉柱田增林

  • Author

    ZHANG Yan1,2 ,HUANG Xuanming1,2 ,PENG Wei3 ,ZHU Mingcheng1,2 , CAO Haidong1,2 ,LIU Yuzhu3 ,TIAN Zenglin1,2

  • 单位

    中煤科工集团西安研究院有限公司陕西省煤矿水害防治技术重点实验室国家能源集团大雁公司

  • Organization
    1. Xi’an Research Institute Co. ,Ltd. ,China Coal Technology and Engineering Group,Xi’an  710054,China; 2. Shaanxi Key Laboratory of Prevention and Control Technology for Coal Mine Water Hazard,Xi’an  710077,China; 3. Dayan Company of China Energy Investment Corporation,Hulunbuir  021122, China
  • 摘要

    为解决扎尼河露天矿矿坑疏排水量大、生产成本高、环保风险大等问题,采用地下混凝土防渗墙、防渗膜大深度垂向隐蔽铺设、高压旋喷注浆、钻孔咬合桩等4种帷幕技术,沿煤层北部隐伏露头建造一座平面长度近6 000 m、最大深度超过50 m、有效厚度>0.6 m的弧线型沟槽灌入式+桩孔压入式落底截水帷幕。

    项目实施过程中攻克了低强度(8~10 MPa)抗渗(P6级)混凝土配合比技术、超长槽段开挖与护壁技术、防渗膜叠覆铺设与连接技术、高掺量粉煤灰-水泥混合浆液注浆充填技术、砾石层中高压旋喷成桩技术等5项技术难题,在帷幕墙建造过程中和结束后,采用取芯验证法、抽水试验法、流场观测法和水量分析法等4种方法检验了帷幕墙的质量与截水效果。

    结果表明混凝土浇筑连续均匀,粉煤灰-水泥混合浆液充填密实、胶结完好,高压旋喷桩和钻孔咬合桩桩径达标、桩体完整;墙体渗透系数为8.34×10-7 cm/s,渗透性达极微透水级;墙体内外两侧最大水位差已达10 m以上;矿坑疏排水量已减少60%,目前仍在减少中。帷幕墙截水效果明显,达到了设计要求。该项目是我国露天煤矿采用综合帷幕技术解决疏排水问题的成功示范。

  • Abstract

    In order to solve the problems of huge drainage volume,high production cost and high environmental risk in Zhanihe open-pit coal mine,four kinds of curtain technologies,such as underground concrete diaphragm wall,large depth vertical concealed laying of anti-seepage membrane,high-pressure rotary jet grouting and secant pile,are used for the first time to build an arc-shaped trench filling type and pile hole pressing type bottom cut-off curtain with a plane length of nearly 6 000 m,a maximum depth of more than 50 m and an effective thickness of more than 0. 6 m along the concealed outcrop in the north of the coal seam. During the implementation of the project,five technical problems have been solved,including low-strength (8 - 10 MPa) impermeable ( P6 grade) concrete mix proportion technology,ultra-long trench excavation and wall protection technology,geomembranes overlay laying and connection technology,high-volume fly ash cement mixed slurry grouting and filling technology,high-pressure jet grouting pile technology in gravel layer. During and after the construction of the curtain wall,the quality and water cut-off effect have been tested by four methods,such as drilling core method,pumping test,flow field observation method and drain- age change analysis method. The results show that the concrete pouring is continuous and uniform,the filling of fly ash cement mixed slurry is dense and the cementation is intact,the diameter of high-pressure rotary jet grouting pile and secant pile is up to the standard,and the pile body is complete. The permeability coefficient of the wall is 8. 34×10-7 cm / s,and the permeability reaches the very micro permeability level. The maximum water level difference between the inside and outside of the wall has reached more than 10 m. The drainage volume of the mine has been reduced by 60% , which is still in the process of reduction. The curtain wall has obvious water interception effect and meets the design re- quirements. The project is a successful demonstration of using a comprehensive curtain technology to solve the drainage problem in China’s open-pit coal mines,with significant social,economic and environmental benefits. The research re- sults of the project have important application value for the development of open-pit coal mine drainage work in China, and have reference significance for the ecological environment protection in the eastern grassland area of China.

  • 关键词

    截水帷幕露天煤矿混凝土防渗墙防渗膜旋喷注浆咬合桩

  • KeyWords

    water cutoff curtain;open-pit coal mine;concrete diaphragm wall;geomembranes;rotary jet grouting;se- cant pile

  • 基金项目(Foundation)
    国家重点研发计划资助项目(2017YFC0804106)
  • DOI
  • Citation
    ZHANG Yan,HUANG Xuanming,PENG Wei,et al. Application of water cutoff curtain in the seepage cutoff and drain- age reduction of open-pit coal mine[ J]. Journal of China Coal Society,2020,45(5):1865 -1873.
  • 相关文章
  • 相关专题
  • 图表
    •  
    •  
    • 扎尼河露天矿充水示意

    图(10) / 表(0)

相关问题

主办单位:煤炭科学研究总院有限公司 中国煤炭学会学术期刊工作委员会

©版权所有2015 煤炭科学研究总院有限公司 地址:北京市朝阳区和平里青年沟东路煤炭大厦 邮编:100013
京ICP备05086979号-16  技术支持:云智互联