• 论文
主办单位:煤炭科学研究总院有限公司、中国煤炭学会学术期刊工作委员会
工业广场保护煤柱开采井筒破损致因及防治技术
  • Title

    Causes of shaft damage in mine plant coal pillar mining and the prevention technology

  • 作者

    程桦喻宏宋海清成浪荣传新姚直书彭世龙

  • Author

    CHENG Hua;YU Hong;SONG Haiqing;CHENG Lang;RONG Chuanxin;YAO Zhishu;PENG Shilong

  • 单位

    安徽理工大学土木建筑学院安徽大学资源与环境工程学院冀中能源峰峰集团有限公司大社矿安徽建筑大学建筑结构与地下工程安徽省重点实验室

  • Organization
    School of Civil Engineering and Architecture, Anhui University of Science and Technology
    School of Resources and Environmental Engineering, Anhui University
    Dashe Mine of Jizhong Energy Fengfeng Group Co. , Ltd.
    Anhui Provincial Key Laboratory of Building Structure and Underground Engineering, School of Civil Engineering, Anhui Jianzhu University
  • 摘要

    针对工业广场保护煤柱开采导致井筒破损的问题,以大社煤矿为工程背景,分析工广煤柱开采井筒围岩移动变形特征,揭示井筒破损致因;提出工广内后续工作面开采防治井筒破坏方案,形成相应的施工技术,并成功应用工程实践。研究表明:该矿工广内92606工作面邻近副井,开采引发的井筒竖向附加力是井筒破坏的致因;如不提前采取防治措施,后续92606外工作面开采,将导致副井井筒发生二次破坏;研究提出的不停产单卸压槽防治方案,具有不影响矿井生产、卸压率高、施工简单、成本低等优点。采用壁后注浆、开切卸压槽、架设密集井圈等技术,顺利完成了该矿不停产防治副井井筒破损工程。监测表明,该井筒竖向和环向应力,均小于井壁极限.承载力,处于安全状态,运行良好,达到了预期效果。

  • Abstract

    Aiming at the shaft damage in mine plant coal pillar mining and its control technology, taking Dashe Coal Mine as the engineering background, the movement and deformation characteristics of surrounding rock in the shaft of mine plant coal pillar mining were analyzed to reveal the causes of shaft damage. The scheme for shaft damage control in the follow-up working face of the project was proposed, and the corresponding construction technology was formed and successfully applied. The research shows that the working face under the mine plant region is adjacent to the auxiliary shaft, and the vertical additional force caused by mining has caused the shaft damage; Without taking preventive measures in advance, the subsequent mining of the working face will lead to secondary damage to the auxiliary shaft. The prevention and control scheme of single pressure relief groove without stopping production was proposed, which has the advantages of not affecting the mine production, high pressure relief rate, simple construction, low cost, etc. After grouting behind the lining, cutting the pressure relief groove, and erecting dense crib ring, the auxiliary shaft damage control project was accomplished without stopping production. The monitoring shows the shaft is in a safe state, as the vertical and hoop stresses are within the ultimate bearing capacity of the shaft wall.

  • 关键词

    工业广场保护煤柱地层沉降井壁破损卸压槽围岩控制

  • KeyWords

    mining of mine plant coal pillar;protection coal pillar;formation settlement;shaft wall damage;pressure relief groove;surrounding rock control

  • 基金项目(Foundation)
    国家自然科学基金项目(51874005,52004003);安徽理工大学高层次引进人才科研启动基金项目(2022yjrc32)
  • DOI
  • 引用格式
    程桦,喻宏,宋海清,等.工业广场保护煤柱开采井筒破损致因及防治技术[J].煤炭工程,2024,56(5):42-50.
  • 相关文章
相关问题

主办单位:煤炭科学研究总院有限公司 中国煤炭学会学术期刊工作委员会

©版权所有2015 煤炭科学研究总院有限公司 地址:北京市朝阳区和平里青年沟东路煤炭大厦 邮编:100013
京ICP备05086979号-16  技术支持:云智互联