• 论文
主办单位:煤炭科学研究总院有限公司、中国煤炭学会学术期刊工作委员会
煤矿综采工作面顶板灾害预警指标及应用研究
  • Title

    Study on early warning index of roof disaster and application to fully-mechanized coal mining face in underground mine

  • 作者

    安泽张江云

  • Author

    ANZe ZHANG Jiang-yun

  • 单位

    北京工业职业技术学院建筑与测绘工程学院四川省煤炭产业集团四川攀枝花煤业(集团)有限责任公司

  • Organization
    School of Architecture and Survey,Bejing Polytechnic College Sichuan Panzhihua Coal Industrial Group Company
    Limited, Sichuan Provincial Coal Industrial Group
  • 摘要
    为获得综采工作面压架事故监测预警指标和预警准则,在分析国内顶板监测系统应用现状的基础上,通过事故案例分析、矿压理论研究和现场实测数据分析,研究综采工作面顶板灾害致灾因素,提出了采场顶板灾害的6个预警指标,即初撑力合格率、安全阀开启率、支架不保压率、不平衡率、顶板周期来压步距、应力和地质异常区域,研究得到了预警指标实时、自动分析算法,建立了综采工作面顶板灾害监测预警平台。该平台在华能集团扎赉诺尔煤业有限责任公司铁北煤矿右三片综放工作面成功应用,通过24 h不间断监测和预警,及时采取有效措施,支架工况显著改善,推进速度加快,年产量由原来的不足250万t提高至350万t。在四川攀枝花煤业(集团)有限责任公司花山煤矿大采高大倾角工作面的成功应用,初撑力水平显著提高,有效解决了支架的防倒防滑问题。同时在皖北煤电集团有限责任公司的成功应用,显著提高了顶板管理水平,避免了多起顶板灾害的发生。
  • Abstract
    In order to have the early warning index and early warning criterion of the powered support jammed accident monitoring and measuring in the fully-mechani zed coal mining face,based on the domestic monitoring and measuring status,with the analysis on the accident cases ,the study on the mine strata pressure theory and the analysis on the site measured data,the paper studied the factors to cause the roof disaster of the fully-mechanized coal mining face and provided six early warning indexes of the roof disaster occurred in the coal mining face ,including the initial setting pressure passed rate. safety valve opening rate,no pressure keeping rate,unbalanced rate,ro of weighting step distance and roof stress as well as the geological abnormal region. A real-time and automatic analysis algorithm of the early warning index was obtained f rom the study and a monitoring and early waning platform of the roof disaster was established for the fully-mechanized coal mining face. The platform was successfully app lied to the Yousanpian fully-mechanized coal mining face in Tiebei Mine, Zhalainuoer Coal Industry Company Limited China Huaneng Group. With 24 h continuous monitorin g and early warning and the on time effective measures conducted,the performances of the powered supports were improved obviously. The advancing rate of the coal mini ng face was speeded up and the annual coal production of the coal miming face was increased from less 2. 50 million t to 3. 50 million t. The platform was successfully app lied to a high cutting and high inclined coal mining face in Huashan Mine of Sichuan Panzhihua Coal Industry Group Company Limited. The initial setting load level was obv iously improved and the falling down and sliding prevention problems of the powered support was effectively solved. Meanwhile,the successful application of the platform t 0 Wanbei Coal and Electric Power Group Corporation Limited obviously improved the roof control level and avoided several roof accidents occurred.
  • 关键词

    顶板灾害预警平台预警指标矿压显现

  • KeyWords

    roof disaster; early warning platform; early warning index; mine strata pressure behavior;

  • 基金项目(Foundation)
    “十二五”国家科技支撑计划资助项目(2012BAB13B02-02);北京市教育委员会面上资助项目(KM201410853004);
  • 相关文章
相关问题

主办单位:煤炭科学研究总院有限公司 中国煤炭学会学术期刊工作委员会

©版权所有2015 煤炭科学研究总院有限公司 地址:北京市朝阳区和平里青年沟东路煤炭大厦 邮编:100013
京ICP备05086979号-16  技术支持:云智互联