• 论文
主办单位:煤炭科学研究总院有限公司、中国煤炭学会学术期刊工作委员会
综放工作面煤柱巷道软岩底板非对称底臌机理与控制
  • Title

    Mechanism and control strategy of asymmetrical floor heave of coal pillar roadway in fully mechanized caving face

  • 作者

    贾后省王璐瑶刘少伟彭博张伟光范凯

  • Author

    JIA Housheng1,2 ,WANG Luyao1 ,LIU Shaowei1,4 ,PENG Bo3 ,ZHANG Weiguang4 ,FAN Kai3

  • 单位

    河南理工大学能源科学与工程学院河南理工大学煤炭安全生产河南省协同创新中心四川华蓥山龙滩煤电有限责任公司新疆工程学院矿业工程与地质学院

  • Organization
    1. School of Energy Science and Engineering,Henan Polytechnic University,Jiaozuo  454003,China; 2. Collaborative Innovation Center of Coal Work Safety, Henan Province, Henan Polytechnic University, Jiaozuo   454003, China; 3. Sichuan HuaYingShan Longtan Coal and Electricity Co. , Ltd. , Guangan  638020,China; 4. Xingjiang Institute of Engineering,Mining Engineering and Geology College,Urumqi  830091,China
  • 摘要

    针对综放工作面煤柱巷道非对称底臌剧烈、支护维护困难、起底工程量大等难题,以大南湖一矿综放工作面煤柱巷道为工程背景,采用理论分析、数值模拟、现场试验等综合研究方法,分析了煤柱巷道围岩周边应力环境特征及其作用下的变形破坏形态。结果表明:煤柱巷道底板强度低下以及在采动影响下围岩应力环境出现非均匀现象,进而导致巷道底板塑性区出现非均匀分布,是造成非对称底臌的内在原因;底臌变形规律监测结果显示,非对称底臌程度与放煤厚度有内在联系,放煤厚度在5.9 m范围内,放煤厚度越大,基本顶岩层破断偏转角度亦越大,巷道围岩周边主应力比值、主应力旋转角度等参数越大,底板塑性破坏引起的非对称底臌变形越剧烈;底板最大塑性破坏深度位置随着主应力方向旋转角度的增加,逐渐向巷道中部位置移动,导致底臌变形最大位置分布不同,同时,煤柱巷道的这种底臌变形可控性较差,现有技术条件下企图采用高强支护是不可行的,控制上应以适应底臌变形为主;然而,当放煤厚度超过5.9 m,基本顶岩层有沿煤柱边缘失稳切落的可能,巷道围岩应力环境趋于原岩应力状态,巷道围岩塑性区分布范围大幅降低,底臌变形较小。据此,以巷道非对称底臌规律为依据,提出了以调整采掘关系、优化巷道底臌硬化方案为主的底臌控制对策,现场应用效果良好,底臌变形量有效减少的同时,巷道底臌处理工作量亦大幅降低。

  • Abstract

    To study the problems such as dramatic asymmetrical floor heave deformation of coal pillar roadway in fully mechanized caving face,difficulty in support and maintenance,theoretical analysis,numerical simulation and field test were adopted. The stress environment,deformation and failure characteristics of the coal pillar roadway in the fully mechanized caving face at Dananhu No. 1 coal mine in China were analyzed. The results demonstrate that the asym- metrical phenomenon of surrounding rock stress environment caused by mining is the intrinsic reason for the asymmet- rical floor heave in the coal pillar roadway. It also leads to a non-uniform distribution of the plastic zone of floor in coal pillar roadway. The degree of asymmetrical floor heave has internal relations with the thickness of caving coal. When the thickness of caving coal is in the range of 5. 9 m,the greater the parameters,such as the thickness of the caving coal,the breaking deflection angle of the strata of main roof,the principal stress ratio and the rotation angle of the prin- cipal stress direction in the stress environment of the roadway, the more obvious deformation of asymmetrical floor heave caused by plastic failure in floor. The maximum plastic failure depth position of the floor gradually moves toward the middle of the roadway as the rotation angle of the principal stress direction increases. It causes a different distribu- tion of the maximum deformation position of floor heave. At the same time,the deformation of the floor heave of the coal pillar roadway is poorly controllable. It is not feasible to attempt to use high-strength support under the current technical condition. The control should mainly be adapted to the floor heave deformation. When the thickness of caving coal more than 5. 9 m,the strata of main roof have the possibility of instability and being cut along the edge of the coal pillar,and the surrounding rock stress environment of the roadway tends to the original rock stress state. Consequently, the distribution range of the surrounding rock plastic zone is greatly reduced in the roadway. The deformation of floor heave is small. Based on the results above,the strategy of floor heave control based on adjusting the relationship of mining and driving,and optimizing the roadway floor heave treatment plan was proposed and good results were ob- tained. With the decrease of deformation of the floor heave,the working volume of floor heave was also greatly re- duced.

  • 关键词

    综放工作面煤柱巷道底臌非对称变形塑性区

  • KeyWords

    fully mechanized caving face;coal pillar roadway;floor heave;asymmetrical deformation;plastic zone

  • 基金项目(Foundation)
    国家自然科学基金资助项目(51604094,51674098);河南省重点研发与推广专项科技攻关资助项目(182102210316)
  • DOI
  • Citation
    JIA Housheng,WANG Luyao,LIU Shaowei,et al. Mechanism and control strategy of asymmetrical floor heave of coal pillar roadway in fully mechanized caving face[J]. Journal of China Coal Society,2019,44(4):1030-1040.
  • 相关文章
  • 相关专题
  • 图表
    •  
    •  
    • 1306工作面回风平巷煤层顶底板岩层结构探测结果

    图(18) / 表(0)

相关问题

主办单位:煤炭科学研究总院有限公司 中国煤炭学会学术期刊工作委员会

©版权所有2015 煤炭科学研究总院有限公司 地址:北京市朝阳区和平里青年沟东路煤炭大厦 邮编:100013
京ICP备05086979号-16  技术支持:云智互联