Title
Technology innovation research on grouting treatment in fracture zone of fully mechanized face with
5.5 m large mining height
-
作者
段云龙马志愿张春文武冲锋王薛庆
-
Author
Duan Yunlong;Ma Zhiyuan;Zhang Chunwen;Wu Chongfeng;Wang Xueqing
-
单位
晋能控股煤业集团 阳泉市上社煤炭有限责任公司石家庄国盛矿业科技有限公司晋能控股煤业集团 太原煤气化荫营煤业有限公司
-
Organization
Yangquan Shangshe Coal Co., Ltd., Jinneng Holding Coal Group
Shijiazhuang Guosheng Mining Technology Co.
Taiyuan Coal Gasification Yinying Coal Industry Co., Ltd., Jinneng Holding Coal Group
-
摘要
针对上社煤炭5.5 m厚煤层一次采全高综采面揭露断层后出现不同特征的冒落空洞和片帮范围,分区域采用不同性能指标的注浆材料进行综合注浆治理,针对揭露煤层厚、采高大(≥5.5 m)、易片帮冒顶等特殊地质条件,对注浆压力等参数进行动态优化以适应大采高煤壁的特殊性,调整注浆顺序等技术参数,控制综采面灾害的延伸范围。应用结果表明,工作面煤壁完整性增强,松散煤岩体固结密实,支架顶梁快速构建了再生胶结假顶支撑层,增强了顶板再次冒落对工作面支架的破坏性冲击,为采煤机滚筒切割之后的及时移架支护作业创造安全的作业环境。该工艺推广应用前景广阔,经济效益和社会效益明显。
-
Abstract
In view of the different characteristics of caving cavity and spalling range after exposing the fault in the 5.5 m thick coal seam of Shangshe Coal, the grouting materials with different performance indexes were used for comprehensive grouting treatment in different regions. In view of the special geological conditions such as thick exposed coal seam, large mining height ( ≥ 5.5 m ), easy spalling and roof fall, the grouting pressure and other parameters were dynamically optimized to adapt to the particularity of large mining height coal wall, adjust the technical parameters such as grouting sequence, and control the extension range of disasters in fully mechanized mining face. The application results showed that the integrity of the coal wall of the working face was enhanced, the loose coal and rock mass was consolidated and compacted, and the roof beam of the support quickly constructed the regenerated cemented false roof support layer, which enhanced the destructive impact of the roof re-caving on the working face support, and created a safe working environment for the timely moving support operation after the shearer drum cutting. The application prospect of this process was broad, and the economic and social benefits were obvious.
-
关键词
煤矿加固煤岩体用聚氨酯材料厚煤层一次采全高综采面冒顶区注浆加固注浆充填
-
KeyWords
polyurethane material for reinforcing coal and rock mass in coal mine;full height fully mechanized mining face in thick coal seam;roof fall zone;grouting reinforcement;grouting filling
-
DOI
-
引用格式
段云龙1,马志愿2,张春文1,武冲锋3,王薛庆1. 注浆治理5.5 m大采高综采面破碎带技术工艺创新研究[J]. 煤炭与化工, 2023, 46(12): 11-13,18..
-
Citation
Duan Yunlong1, Ma Zhiyuan2, Zhang Chunwen1, Wu Chongfeng3, Wang Xueqing1. Technology innovation research on grouting treatment in fracture zone of fully mechanized face with
5.5 m large mining height. CCI, 2023, 46(12): 11-13,18..
-