Technology of Once Blasting Large Cross Section Roadway Heading and Surrounding Rock Control in Over 1 000 m Deep Underground Mine
-
作者
魏礼刚张辉孙永慧
-
单位
山东能源新汶矿业集团有限责任公司华丰煤矿煤炭科学研究总院开采设计研究分院陕西南梁矿业有限公司
-
摘要
为解决千米深井高应力大断面巷道掘进速度缓慢及巷道围岩控制难度大的问题,采用地应力测试、数值模拟及现场观测的方法,分别对大断面巷道分阶梯爆破成巷和一次爆破成巷的围岩应力、位移及塑性破坏特征进行了研究,并对2种成巷方式采用同种支护条件下巷道表面位移进行观测。结果表明:一次爆破成巷避免了爆破扰动对巷道围岩多次爆破扰动破坏,巷道围岩变形相对容易控制,且施工工艺较简单,掘进速度可由0.67 m/d提高至2.00~3.00 m/d。
-
Abstract
In order to solve the slow heading speed of the high stress large cross section roadway and high difficult surrounding rock control of the roadway in over
1 000 m deep mine, a ground stress measurement, numerical simulation and site observation methods were applied to the study on the stress, displacement and plastic
failure features of the mine large cross section roadway with the bench heading and once blasting heading and to the observation on the surface displacement of the mi
ne roadway.The results showed that the once blasting heading roadway could avoid the blasting disturbance to the multi blasting disturbance and failure of the roadway
surrounding rock, the deformation of the roadway surrounding rock could be relatively easy controlled and the construction technique would be relative simple.Thus the
heading speed could be improved from 0.67 m/d to 2.00-3.00 m/d.
-
关键词
千米深井大断面一次爆破成巷分阶梯爆破成巷围岩控制
-
KeyWords
over 1 000 m deep underground mine;large cross section;once blasting mine roadway heading;bench blasting roadway heading;surrounding rock contro |;
-